Airport Muenster-Osnabrueck
Rehabilitation S/L - Railway
- Project period: 2021 to 2022
- Investment: approx. 2.35 mill. € Technical equipment
Rehabilitation of the Runway
- Renovation of the runway with flight operations partially in progress. Two-week runway closure for main works
- Modernization of the lighting system and conversion to LED lighting
- Consideration of the standard DIN EN 62870 (SELV / PELV)
- Renewal of the following Airfield Ground Lighting systems: APH, APL, RSR, THR, RWE, RCL, REH, TDZ, STB AIBIC, TGS, SFL 07 and SFL 25
- In stations 25 and 07, new power - transformers and control cabinets
- Control cabinets and circuits with series circuit isolators (Cut – Outs)
- Examination of the existing emergency power supply system Station 25 to ensure safe power supply of the systems requiring emergency power, in particular the AGL system